Confirmation of report
If job's property confirmed is set to user then report of that job must be confirmed. If report is not confirmed then it will be
shown in reminder in report to confirm table.
Report of unplanned maintenance
Open "component manager", select component for unplanned maintenance report. Select "unplanned job rep." button and
open "unplanned maintenance report" dialog.
Fill in report dialog.
Fields required:
- description: should contain information about result of work and/or special activities done e.g. replace of some parts,
repairs etc.
- date: should be not later than date (today). In future reporting is not allowed.
Advanced report: advanced report can be enclosed.
Unplanned maintenance job has number UM 00000
Report of work order
Open "component manager", select component with work order to report. In work orders table select order to report.
Select "edit work order" button then open order. In "work order" dialog window select button "report work order".
Fill in report dialog.
Fields required:
- description: should contain information about result of work and/or special activities done e.g. replace of some parts,
repairs etc.
- date: should be not later than date (today). In future reporting is not allowed.
- completion percent: work orders can be partly completed. If report does not cover 100% of work order then another
completion value should be set.
Advanced report: advanced report can be enclosed.